BEAVER CREEK MEDICAL OFFICE BUILDING

Our Mission

To support our client’s vision by developing, constructing, and maintaining buildings that enhance our community.

Our Vision

To pioneer a unique client experience built on our tradition of honorable professionals- true to their word, competent, and dependable.

What We Value

Our Clients who collaborate with us to create a positive experience.

Our People who are dedicated and passionate about their work.

Our Business Partners who are also honorable professionals.

Our Work Environment which is safe, enjoyable, and respectful.

Our Community which provides meaning for our life’s work.

Play Video

HISTORY OF EXCELLENCE

In the past 20 years, R. E. Lee & Son has completed more than 1600 projects, ranging from historical renovations, to large industrial projects.

WHAT WE DO.

  • General Contracting
  • Construction Management
  • Design / Build
  • Pre-Construction Services

PRECONSTRUCTION SERVICES

  • Providing Estimates
  • Construction Schedules
  • Assist Design Team throughout design
  • Provide Value Engineering

HOW WE WORK

We work in an open book format

VALUE ENGINEERING

The systematic application of function oriented techniques to analyze & improve the value of a project.

  • Value can be increased by improving function or reducing cost

 

  • Any accepted items will have been fully endorsed by Owner, Designer, & Contractor

 

  • Accepting not only the change in cost but change in function.

EXAMPLES

  • Reduce floor to floor heights. Each floor could be reduced by 1’, including garage. Garage to 1st: 10’, 1st to 2nd: 14’-4”, 2nd to roof” 13’-9”. Previously discussed on June 6, 2019.
  • Eliminate Lobby at Garage. Previously discussed on June 6, 2019.
  • Alternate to spray insulation on Garage ceiling. Not sure how insulation will work with lights that are specified anyway.
  • Eliminate sunshades. Subject to ARB approval.
  • Alternate wall and ceiling finishes in Elevator Lobby. Painted gypsum board in lieu of Aluminum “Longboard” panels on walls. Acoustic ceiling in lieu of aluminum longboard panes.
  • Reduce level of finishes at Stair 1. Steel handrails in lieu of wood. Delete drywall finish on wall and paint concrete / CMU. Delete acoustical ceiling.
  • Delete acoustical ceiling at Stair 2.
  • Use 10 mil vapor barrier at slab on grade in lieu of Stego.
  • Eliminate batt insulation in walls above roof level.
  • Credit amount to perform sprinkler piping at 1st and 2nd floors as part of tenant upfit.
  • Credit amount to perform HVAC work at 1st and 2nd floors as part of tenant upfit.
  • Credit amount to perform lighting work at 1st and 2nd floors as part of tenant upfit.

LOGISTICS PLAN

PHASE 1

PHASE 2

PRELIMINARY MILESTONE SCHEDULE

SAFETY

SAFETY FOR LIFE

R. E. Lee & Son, Inc. is committed to building a safety culture that ensures all employees and trade partners make it home safely to their families. 

All workers on site will be required to attend a site-specific safety orientation prior to beginning work.

All workers on site will be required to attend a site-specific safety orientation prior to beginning work.

During 2019, R. E. Lee & Son, Inc. had no lost time accidents. 

During 2018 R. E. Lee & Son, Inc had ZERO OSHA recordables.

R. E. Lee & Son, Inc. believes that providing all workers on site with a clear method to report hazards is the key to incident prevention and saving lives. 

Virginia BEST Program

In 2018 R. E. Lee & Son, Inc. reached the goal of being the second contractor in the Commonwealth of Virginia to apply to the Virginia BEST Program, a partnership between VOSH and Virginia AGC.

The BEST Program, which stands for Building Excellence in Safety, Health and Training, is designed to encourage and recognize AGCVA members who implement safety and health management systems to benefit construction workers.

PRICING